The correct answer is 15.69% If the budget is $100,000 for the projects shown below? What is the opportunity cost of capital? (note that you
The correct answer is 15.69%
If the budget is $100,000 for the projects shown below? What is the opportunity cost of capital? (note that you need to fill in the missing values)
Project | Life (years) | First Cost | Annual Benefit | Salvage Value | IRR |
1 | 15 | $22,000 | $4000 | $0 | 16.29% |
2 | 15 | 22,000 | 3200 | 10,000 | 13.22 |
3 | 20 | 22,000 | 3300 | 0 | |
4 | 15 | 22,000 | 4500 | 0 | 15.69 |
5 | 20 | 22,000 | 4500 | -20,000 | 19.35 |
6 | 10 | 22,000 | 5800 | 0 | 23.05 |
7 | 15 | 22,000 | 4000 | 10,000 |
Interest Factor Calculator
17.80% | ||
15.69% | ||
16.29% | ||
13.89% |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started