Question

1 Approved Answer

The correct answer is 15.69% If the budget is $100,000 for the projects shown below? What is the opportunity cost of capital? (note that you

The correct answer is 15.69%

If the budget is $100,000 for the projects shown below? What is the opportunity cost of capital? (note that you need to fill in the missing values)

Project Life (years) First Cost Annual Benefit Salvage Value IRR
1 15 $22,000 $4000 $0 16.29%
2 15 22,000 3200 10,000 13.22
3 20 22,000 3300 0
4 15 22,000 4500 0 15.69
5 20 22,000 4500 -20,000 19.35
6 10 22,000 5800 0 23.05
7 15 22,000 4000 10,000

Interest Factor Calculator

17.80%
15.69%
16.29%
13.89%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Market Regulations And Finance

Authors: Ratan Khasnabis, Indrani Chakraborty

2014th Edition

8132217942, 978-8132217947

More Books

Students also viewed these Finance questions

Question

7. Identify six intercultural communication dialectics.

Answered: 1 week ago