The cost formula for wages and salaries is $2,030 per month plus $409 per birth. For May, the planned activity for 112 births, but the
The cost formula for wages and salaries is $2,030 per month plus $409 per birth. For May, the planned activity for 112 births, but the actual level of activity was 114 births. Actual wages and salaries for the month was $50,800. Wages and salaries in the planning budget for May would be closest to...