The cost of a new plant was built in Arlington, VA with a capacity of 560 products per day is $25,900,000. Estimate the cost of
The cost of a new plant was built in Arlington, VA with a capacity of 560 products per day is $25,900,000. Estimate the cost of a new plant with a capacity of 840 products per day constructed in Atlanta, GA. The cost-capacity exponent for this type of plant is 0.58. The location index for Arlington is 1.21 and the location index for Atlanta is 1.03