Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The CPM model for a project returns the following slack times. Based on this information, what activities are on the critical path? Activity M N

The CPM model for a project returns the following slack times. Based on this information, what activities are on the critical path?

ActivityMNPRSTU
Slack0045102

The activities on the critical path are:

M,N,T

All of the activities must be completed so all the activities are on the critical path

P,R,S,U

S,U

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Purchasing and Supply Chain Management

Authors: W.C Benton

3rd edition

78024110, 978-0078117091, 78117097, 978-0078024115

More Books

Students also viewed these General Management questions

Question

What are the Lewis electron dot diagrams of PO33 and PO43?

Answered: 1 week ago