Question
1 Approved Answer
The critical path for the network activities shown below is with duration A-D-E; 5 B) B-E; 6 B-C-E; 12 ACE;10 B-D-E; 7
The critical path for the network activities shown below is with duration A-D-E; 5 B) B-E; 6 B-C-E; 12 ACE;10 B-D-E; 7