Question
1 Approved Answer
The critical path for the network activities shown below is ________ with duration ________. Activity Duration (Week) Immediate Predecessors Q 2 -- P 6 --
The critical path for the network activities shown below is ________ with duration ________. Activity Duration (Week) Immediate Predecessors Q 2 -- P 6 -- Y 6 P, Q X 1 P, Q Z 2 Q, Y, X Question 99 opt