The critical path is O A. The path of tasks on a network diagram with the longest total duration. B. The path of tasks on
The critical path is O A. The path of tasks on a network diagram with the longest total duration. B. The path of tasks on a network diagram representing the minimum total duration for the project. C. The tasks with zero or negative float. D. All answers are correct