The critical path of a project has the duration with mean 68 days and variance 78. A second path in the project from start to

The critical path of a project has the duration with mean 68 days and variance 78. A second path in the project from start to end has the duration 59 days and variance 140. The probability of completion of critical path in 80 days is 91%, while the probability of completion of the non-critical path in 80 days is 96%. What is the probability of completion of the project in 80 days?

91%

96%

87%

84%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Probability With Applications and R

Authors: Robert P. Dobrow

1st edition

1118241257, 1118241258, 978-1118241257

More Books

Students explore these related Mathematics questions