Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The Crosby management team would like you to consult and evaluate the project management processes in terms of how they improve the business value of

The Crosby management team would like you to consult and evaluate the project management processes in terms of how they improve the business value of Crosby. They would like you to present your findings to the management team at their next meeting.

You will need to complete an earned value analysis (EVA) based on the case and identify the business value components prior to developing your presentation for the management team.

Create an 8- to 10-slide presentation in which you:

  • Identify business values in their project management processes.
  • Discuss how the current processes can be adjusted to improve the project outcomes and maximize business value.
  • Identify at least 3 additional processes that can be used to improve the earned business value of Crosby.
  • Identify other relevant artifacts and resources of project management processes across the project's life cycle that can affect the business outcomes at Crosby.Crosby Manufacturing Corporation

"I've called this meeting to resolve a major problem with our management cost and control system

[MCCS]," remarked Wilfred Livingston, president of Crosby Manufacturing Corporation. "We're having one

hell of a time trying to meet competition with our antiquated MCCS reporting procedures. Last year we

were considered nonresponsive to three large government contracts because we could not adhere to the

customer's financial reporting requirements. The government has recently shown a renewed interest in

Crosby Manufacturing. If we can computerize our project financial reporting procedure, we'll be in great

shape to meet the competition head on. The customer might even waive the financial reporting

requirements if we show our immediate intent to convert."

Crosby Manufacturing was a $250-million-a- year electronics component manufacturing firm in 2005, at

which time Wilfred "Willy" Livingston became president. His first major act was to reorganize the 700

employees into a modified matrix structure. This reorganization was the first step in Livingston's long-

range plan to obtain large government contracts. The matrix provided the customer focal point policy that

government agencies prefer. After three years, the matrix seemed to be working. Now the company could

begin the second phase, an improved MCCS policy.

On October 20, 2007, Livingston called a meeting with department managers from project management,

cost accounting, management information systems (MIS), data processing, and planning. Livingston: "We

have to replace our current computer with a more advanced model so as to update our MCCS reporting

procedures. In order for us to grow, we'll have to develop capabilities for keeping two or even three

different sets of books for our customers. Our current computer does not have this capability. We're

talking about a sizable cash outlay, not necessarily to impress our customers, but to increase our

business base and grow. We need weekly, or even daily, cost data so as to better control our projects."

MIS manager:

"I guess the first step in the design, development, and implementation process would be

the feasibility study. I have prepared a list of the major topics which are normally included in a feasibility

study of this sort." [See Exhibit I.]

Livingston:

"What kind of costs are you considering in the feasibility study?"

MIS manager:

"The major cost items include input-output demands; processing; storage capacity; rental,

purchase, or lease of a system; nonrecurring expenditures; recurring expenditures; cost of supplies;

facility requirements; and training requirements. We'll have to get a lot of this information from the

Electronic data processing (EDP) department."

EDP manager:

"You must remember that, for a short period of time, we'll end up with two computer

systems in operation at the same time. This cannot be helped. However, I have prepared a typical

(abbreviated) schedule of my own. [See Table I.] You'll notice from the right-hand column that I'm

somewhat optimistic as to how long it should take us."

Livingston:

"Have we prepared a checklist on how to evaluate a vendor?"

EDP manager:

"Besides the benchmark test, I have prepared a list of topics that we must include in

evaluating any vendor. (See Exhibit II.). We should plan to call on or visit other installations that have

purchased the same equipment and see the system in action. Unfortunately, we may have to commit real

early and begin developing software packages. As a matter of fact, using the principle of concurrency, we

should begin developing our software packages right now.

EXHIBIT I. FEASIBILITY STUDY

Objectives of the study

Costs

Benefits

Manual or computer-based solution?

For use by University of Phoenix only. Copyright 2021 John Wiley & Sons, Inc.

Crosby Manufacturing Corporation Case Study

Page 2 of 3

Objectives of the system

Input requirements

Output requirements

Processing requirements

Preliminary system description

Evaluation of bids from vendors

Financial analysis

Conclusions

TABLE I TYPICAL SCHEDULE (IN MONTHS)

Activity

Normal Time to Complete Crash Time to Complete

Management go-ahead

0

0

Release of preliminary system specs. 6

2

Receipt of bids on specs. 2

1

Order hardware and systems software

2

1

Flow charts completed

2

2

Applications programs completed

3

6

Receipt of hardware and systems software

3

3

Testing and debugging done

2

2

Documentation, if required

2

2

Changeover completed

22

15*

* This assumes that some of the activities can be run in parallel, instead of in series.

EXHIBIT II. VENDOR SUPPORT EVALUATION FACTORS

Availability of hardware and software packages

Hardware performance, delivery, and past track record

Vendor proximity and service-and-support record

Emergency backup procedure

Availability of applications programs and their compatibility with our other systems

Capacity for expansion

Documentation

Availability of consultants for systems programming and general training

Who burdens training cost?

Risk of obsolescence

Ease of use

Livingston:

"Because of the importance of this project, I'm going to violate our normal structure and

appoint Tim Emary from our planning group as project leader. He's not as knowledgeable as your people

are in regard to computers, but he does know how to lay out a schedule and get the job done. I'm sure

your people will give him all the necessary support he needs. Remember, I'll be behind this project all the

way. We're going to convene again one week from today, at which time I expect to see a detailed

schedule with all major milestones, team meetings, design review meetings, et cetera, shown and

identified. I'd like the project to be complete in 18 months, if possible. If there are risks in the schedule,

identify them. Any questions?"

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Sales And Marketing

Authors: James R Abbey

5th Edition

0866123253, 9780866123259

More Books

Students also viewed these General Management questions