The cumulative budgeted cost is Question 15 options: the aggregate estimated costs of all the activities. the amount budgeted to accomplish the work scheduled to
The cumulative budgeted cost is Question 15 options: the aggregate estimated costs of all the activities. the amount budgeted to accomplish the work scheduled to a point in time in the project. the committed costs for an activity. the sum of all the funds expended to a point in time in the project