Question

1 Approved Answer

The data of a project is as below. Work completed 40%, Work scheduled 65%Baseline cost 2, 00,000 Cost incurred 1, 10,000The SPI will be equal

The data of a project is as below.

Work completed 40%, Work scheduled 65%Baseline cost 2, 00,000 Cost incurred 1, 10,000The SPI will be equal to ?

A. 0.615

B. 0.75

C. 0.725

D. 0.625

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essential Quantitative Methods For Business Management And Finance

Authors: Les Oakshott

7th Edition

1352005697, 978-1352005691

More Books

Students also viewed these General Management questions

Question

What law required department to ovtain search warrant

Answered: 1 week ago