The delivery of a key component of your final product has been delayed by 15 days. You are expected to do a demo of the
The delivery of a key component of your final product has been delayed by 15 days. You are expected to do a demo of the prototype for your customer in 10 days. You are meeting with the team to see if you can deliver a limited version of the product without the key component. What are you trying to come up with? A work around or avoidance strategy ) A risk mitigation plan A risk management plan A risk response plan