Question
1 Approved Answer
The demand each week is 30. The standard deviation of demand is 5 a week. The lead time is 3 weeks. z = 1.65 in
The demand each week is 30. The standard deviation of demand is 5 a week. The lead time is 3 weeks. z = 1.65 in the safety stock calculation, What is the reorder point? Group of answer choices 35.2 64.2 90 104.3