The demand for sabassembly S is 100 units in week 7 . Each unit of $ requres 2 unts of T and 2 units of U. Each unit of T requires 1 unt of V,2 unis of W, and 1 unit of X. Fhaly, each unit of U. recuires 2 units of Y and 3 units of Z. One firm manufactures all iteme. It takes 2 weeke to make S,1 weok to make T, 2 weeks to make U, 2 weeks to mako V,3 weeks to make W, 1 week to make X,2 weeks to make Y, and 1 woek to make Z. Cick the kon to view the product sructure and the time-phased product structure Click the icon to view the on-hand imventory. Suppose that in addision to 100 units of S, there is also a demand tor 20 units or U, which is a component of S. The 20 unts of U are noedod for maintenanse purposes. These unite are noosod in week f. Additionaly, a new order has been received Sor 90 units of S due in weok 8 . Modity the net malerial requirements plan to reflect these changes. Construct a rien net material requiements plan (onter your responses as wholb numbers). The demand for sabassembly S is 100 units in week 7 . Each unit of $ requres 2 unts of T and 2 units of U. Each unit of T requires 1 unt of V,2 unis of W, and 1 unit of X. Fhaly, each unit of U. recuires 2 units of Y and 3 units of Z. One firm manufactures all iteme. It takes 2 weeke to make S,1 weok to make T, 2 weeks to make U, 2 weeks to mako V,3 weeks to make W, 1 week to make X,2 weeks to make Y, and 1 woek to make Z. Cick the kon to view the product sructure and the time-phased product structure Click the icon to view the on-hand imventory. Suppose that in addision to 100 units of S, there is also a demand tor 20 units or U, which is a component of S. The 20 unts of U are noedod for maintenanse purposes. These unite are noosod in week f. Additionaly, a new order has been received Sor 90 units of S due in weok 8 . Modity the net malerial requirements plan to reflect these changes. Construct a rien net material requiements plan (onter your responses as wholb numbers)