Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The demand for subassembly S is 1 0 0 units in week 7 . Each unit of S requires 2 units of T and 2

The demand for subassembly S is 100 units in week 7. Each unit of S requires 2 units of T and 2 units of U. Each unit of T requires 1 unit of V,1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S,2 weeks to make T,2 weeks to make U,2 weeks to make V,2 weeks to make W,1 week to make X,2 weeks to make Y, and 2 weeks to make Z.
LOADING... Click the icon to view the product structure and the time-phased product structure.
Part 2
In addition to 100 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used).
Week
Lead Time
Item
1
2
3
4
5
6
7
(weeks)
S
Gross req
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
Order release
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

Chinese 1st Edition

7508679814, 978-7508679815

More Books

Students also viewed these General Management questions