The demand for subassembly S is 100 units in week 7. Each unit of S requires one unit of T and 0.5 unit of U.

The demand for subassembly S is 100 units in week 7. Each unit of S requires one unit of T and 0.5 unit of U. Each unit of T requires one unit of V, two units of W, and one unit of X. Finally, each unit of U requires 0.5 units of Y nd three unit of Z. One from manufacturers all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y and 1 week to make Z.

  1. Construct a product structure and a gross material requirements plan for the dependent inventory items. Identify all level, parents and components.

  1. Construct a net material requirements plan (Item S & T only) for the product structure and the following on hand inventory.

Items On hand inventory Items On hand inventory
S 20 W 30
T 20 X 25
U 10 Y 15
V 30 Z 10

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management A Competitive Advantage Approach Concepts

Authors: Fred R. David, Forest R. David

15th edition

978-0133444896, 133444791, 9780133444858, 133444899, 133444856, 978-0133444797

More Books

Students also viewed these General Management questions

Question

Analyze financial reporting for intercorporate investments.

Answered: 1 week ago

Question

Analyze financial statement disclosures for investment securities.

Answered: 1 week ago