The demand for subassembly S is 110110 units in week 7. Each unit of S requires 11 unitnothing of T and 11 unitnothing of U.
The demand for subassembly S is 110110 units in week 7. Each unit of S requires 11 unitnothing of T and 11 unitnothing of U. Each unit of T requires 11 unitnothing of V, 22 unitss of W, and 11 unitnothing of X. Finally, each unit of U requires 11 unitnothing of Y and 22 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 11 weeknothing to make T, 2 weeks to make U, 22 weekss to make V, 33 weeks to make W, 11 weeknothing to make X, 2 weeks to make Y, and 11 weeknothing to make Z.
Suppose that in addition to 110110 units of S, there is also a demand for 3030 units of U, which is a component of S. The 3030 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the net material requirements plan to reflect this change.
U Gross reg 90 | 30 On hand 40 | 0 50 | 30 Net req Order receipt receipt 50 | 30 Order release 50 | 30 70 Gross req V On hand 30 40 Net req 40 Order receipt Order release 40 w Gross req 140 On hand 25 115 Net req 115 Order receipt Order release | 115 Gross req 70 On hand 25 45 Net req 45 Order receipt Order release 45 Gr Gross req On hand Net req Order receipt Order release U Gross reg 90 | 30 On hand 40 | 0 50 | 30 Net req Order receipt receipt 50 | 30 Order release 50 | 30 70 Gross req V On hand 30 40 Net req 40 Order receipt Order release 40 w Gross req 140 On hand 25 115 Net req 115 Order receipt Order release | 115 Gross req 70 On hand 25 45 Net req 45 Order receipt Order release 45 Gr Gross req On hand Net req Order receipt Order release
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started