Question
The demand for subassembly S is 120 units in week 7. Each unit of S requires 2 units of T and 1 Unit of U.
The demand for subassembly S is 120 units in week 7. Each unit of S requires 2 units of T and 1
Unit of U. Each unit of T requires 1 unit of V, 2 units of W, and 2 units of X. Finally, each unit of U requires
1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 2 weeks
to make T, 2 weeks to make U, 2 weeks to make V, 2 weeks to make W, 1 week to make X, 2 weeks to make Y, and 2 weeks to make Z.
.
Part 2
In addition to 120 units of S, there is also a demand for 20 units of U, which is a component of S. The
20 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change for each week For S, T, U, V, W, X, Y, and Z.(type 0 if the input box is not used).
WeekLead TimeItem 1234567(weeks)SGross req Order release 2
Part 3
T Gross Req
Order Release 2
U Gross Req
Order Release 2
V Gross Req
Order Release 2
W Gross Req
Order Release 2
X Gross Req
Order Release 1
Y Gross Req
Order Release 2
Z Gross Req
Order Release 2
More Info The time-phased product structure
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started