Question
The development and construction of the project will take 3 years, and the project will operate for 30 years. The riskless rate is 5%; the
The development and construction of the project will take 3 years, and the project will operate for 30 years.
The riskless rate is 5%; the rate of return on the market portfolio is 10%, and the projects beta is 1.2. DCC has no debt.
DNFC expects to spend $250,000 for land one year after the contract is awarded (t = 1). Construction of the building will cost $2 million, and the equipment will cost $3 million, both of which will be cash outflows at t = 2.
The life of the building is 30 years, and it will be depreciated toward a salvage value of $50,000. The equipment has a five-year useful life with no salvage value. The equipment will be replaced at five-year intervals for $3 million upon each replacement.
Straight-line deprecation will be used (over years t = 4, t = 8, etc.). To support operations, DNFC expects to need $20,000 in additional cash, to invest $60,000 in accounts receivable and $80,000 in inventory, and to maintain $60,000 in accounts payable. The investment in net working capital occurs at the start of operations (t = 3). The revenues from the project will amount to $800,000,fixed costs will be $100,000, and variable costs will be $150,000, all on an annual basis. At the end of the project, the firm is expected to restore the surrounding area for $420,000, The firms marginal tax rate is 21%. The value of the land is expected to be constant over the project's life, and the building can be sold for $150,000 at the end of the project.
What is the minimum amount the municipality would have to pay DNFC when the contract is awarded (t = 0) to make it worthwhile for DNFC to undertake the project?
Hint: Find the projects cost of capital and create a by-item capital budgeting analysis Excel spreadsheet like Table 10-4 (page 258) in the EFS textbook). Also, look at the Perma Filter example (Canvas Modules, Chapter 10 Additional Resources, and Chapter 10.3 (Parts 1 & 2) videos) to guide you through setting up the spreadsheet. Finally, remember that a project must have AT LEAST an NPV = 0 so shareholders achieve the desired rate of return and the share price is not negatively impacted.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started