Question
The diagram below shows the precedence relationships and task times (in minutes) for assembly of a product. The table provides the task times for each
The diagram below shows the precedence relationships and task times (in minutes) for assembly of a product. The table provides the task times for each task.
Task Positional
Task Time Weight
A 6 _____
B 4 _____
C 5 _____
D 7 _____
E 5 _5__
F 3 _3__
G 2 _2__
(a) Fill in the positional weights in the table above for A, B, C and D.
(b) Using the positional weights from the table and a cycle time of 9 minutes per workstation, assign the 7 tasks to workstations using the ranked positional weight technique. Show all your work and indicate below the sequential assignments of the tasks to workstations (1st, 2nd, 3rd, etc.) below.
Task assigned 1st = ____ assigned to WS ____
Task assigned 2nd = ____ assigned to WS ____
Task assigned 3rd = ____ assigned to WS ____
Task assigned 4th = ____ assigned to WS ____
Task assigned 5th = ____ assigned to WS ____
Task assigned 6th = ____ assigned to WS ____
Task assigned 7th = ____ assigned to WS ____
c) What is the efficiency delay for your solution in part b) using a cycle time of 9 minutes?
d) Find the best balance for this data for a cycle time of 9 minutes (using the fewest workstations and most even balance).
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started