The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A

The duration and resource usage for each activity are showed in the table below.

image text in transcribed

Activity Predecessor Total Processing Time (days) # of painters required/day A --- 0.5 2 B A 1 2 C B 1 1 D B 1 2

How many painter-days are required for the whole project?

\begin{tabular}{|c|c|c|c|} \hline Activity & Predecessor & \begin{tabular}{l} Total \\ Processing \\ Time \\ (days) \end{tabular} & \begin{tabular}{l} \# of painters \\ required/day \end{tabular} \\ \hline A & --- & 0.5 & 2 \\ \hline B & A & 1 & 2 \\ \hline C & B & 1 & 1 \\ \hline D & B & 1 & 2 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Planned Giving Management Marketing And Law

Authors: Ronald R. Jordan, Katelyn L. Quynn

3rd Edition

0471679798, 978-0471679790

More Books

Students also viewed these General Management questions