Question
1 Approved Answer
The duration of the critical path for the network activities shown below is table[[Activity,Duration,Immediate],[Predecessors,,],[A,4,--],[B,2,A],[C,9,--],[D,4,A],[E,5,B,C,D]] Select one: a. 13 days
The duration of the critical path for the network activities shown below is \table[[Activity,Duration,Immediate],[Predecessors,,],[A,4,--],[B,2,A],[C,9,--],[D,4,A],[E,5,B,C,D]] Select one: a. 13 days