The earned value system starts with the time-phased costs that provide the project baseline, which is called the Multiple Choice O planned budgeted value of
The earned value system starts with the time-phased costs that provide the project baseline, which is called the Multiple Choice O planned budgeted value of work scheduled. O planned budgeted value of work completed. O earned value of work scheduled. O scheduled value of work scheduled. scheduled value of work completed