Question
The Employer, New Gold Mining, and the Contractor, Quick Construction, entered into a FIDIC 1999 Conditions of Contract For Plant and Design Build (Yellow Book)
The Employer, New Gold Mining, and the Contractor, Quick Construction, entered into a FIDIC 1999 Conditions of Contract For Plant and Design Build ("Yellow Book") contract. The works comprises the design and construction of a new waste-water treatment plant.
The Appendix to Tender, issued together with the Invitation to Tender, contained the following entries:
13.8 | Adjustment for Changes in Cost | The Contract Price is not subject to Contract Price Adjustment |
14.2 | Advance Payment | Advance Payment by the Employer is 15% of the Accepted Contract Amount for this Contract |
The Particular Conditions of Contract, issued together with the Invitation to Tender, contained amongst others, the following:
13.8 | 13.8.1 Adjustment for Changes in Cost | Deleted and replaced by: The price is fixed and firm with the exception of Forex fluctuations. |
13.8.2 Method of price adjustment for Forex fluctuations | The value of any Plant and Materials imported from outside South Africa shall be inserted in Schedule 2.6 "Schedule of Imported Equipment" as found in Book 2 of 4. Any Plant and Materials not inserted in this schedule shall be deemed to be manufactured in South Africa for the purposes of forex variation calculations. | |
13.8.2.1 Plant and Materials imported from outside South Africa | Adjustment to the Contract price for the supply, delivery and storage of any Plant and Materials imported from outside the Republic of South Africa will be permitted only in respect of the following variables: Variations in Rates of Exchange, and Variations in Customs Surcharge and Customs Duty | |
14.1 | The Contract Price | Delete Sub-Paragraphs (c) and (d) and replace with the following: (c) Prices entered in the Schedules of Quantities, together with any schedule of rates for which provision is made in a Schedule, will be used for calculating the value of completed works for the purpose of interim payments or for determining the value of changes, omissions and additions for variation instructions when in the opinion of the Engineer such prices are applicable. |
The amounts of work and material given in the Schedules of Quantities are not to be considered as limiting or extending the amount of work to be done or material to be supplied by the Contractor. The percentage completion of the amounts of work and materials given in the Schedules of Quantities shall be determined by the Engineer for interim payment certificates when checking the Contractor's Statement referred to in Sub-Clauses 14.3 and 14.6. | ||
14.4 | Schedule of Payments | Delete this Sub-Clause |
When submitting its offer, the Contractor put forward the below-mentioned amendments to the contract. These changes were accepted by the employer.
13.8 | Adjustment for Changes in Cost | The Contract Price is fixed and firm provided the Contractor is not delayed in executing the project through no fault of the Contractor. Should the Contractor be delayed in the execution of the Contract mutually agreed escalation indices will be applied with the tender Base Date (i.e., May 2019). |
14.2 | Advance Payment | Replace 15% with 30% |
14.3 | Interim Payment certificates | Payment terms will be as follows: 30% of Contract Price on award of Contract as an Advance Payment against an advance payment bond. 15% of Contract Price on proof of shipping documents of the DAF Unit 10% of Contract Price on proof of shipping documents of the membranes 10% of Contract Price on the delivery of the membranes to Site 5% of the Contract Price on the delivery of the DAF Unite to Site 10% of the Contract Price on Plant ready for commissioning 10% of the Contract Price on completion of commissioning 10% of the Contract Price on successful completion of the Performance Test. |
The duration of the project has been extended, amongst others due to variations instructed by the Engineer. Delays have also been experienced to completion due to changed circumstances stemming from COVID-19. These included the introduction of new legislation by the Government of the Country where the site is situated. The contractor made an allowance for possible price increases when he submitted his initial price to the Employer. Due to all of these delays, however, the Contractor is faced with losses on the project since the cost of Plant and Materials have escalated.
Question1(d) TheEmployerhassuspendedthe workduetotheimpact ofCOVID 19.SincetheEmployeris,itself,experiencing financialdifficulties,theEmployerwantstoContractortorepaythefullamountthatithas paidtoitonthebasisit wasmerelyanadvancepayment. AdvisetheEmployerofitsprospectsof successingettingtheContractortorepaytheamountinquestion.
Question1(b)
Wouldithavebeenpreferential,inyouropinion,fortheParties,toenterintoaRebBookinstead oftheYellowbookgiventhe factthatcost orPlantandMaterialshavebecomesubjecttohuge fluctuationin price?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started