The end product A is made from components B, and C. B is made from D,E, and F. What is the replenishment lead time for
The end product A is made from components B, and C. B is made from D,E, and F. What is the replenishment lead time for A, assuming there are no inventories? 1 week 6 weeks 7 weeks 8 weeks