The Enterprise Change Assessment (ECA) for CR 00135 has been completed and the recommended actions have been recorded. Supporting datasets for each item are identified

The Enterprise Change Assessment (ECA) for CR 00135 has been completed and the recommended actions have been recorded. Supporting datasets for each item are identified by type, number, and revision. The datasets impacted by the proposed change are identified in the illustration.

Incremental cost breakdowns for material, direct labor, and overhead for items before the change, and the new items after the change, are to be calculated. Rates for creating or revising each of the dataset types are provided on the next page.

Note:

Existing item numbers are shown inside the boxes and based on the ECA results; new item numbers are outside the boxes.

Datasets for new item numbers must be created new; datasets for an unchanged item number are to be revised. image text in transcribed Dataset cost standards for nonrecurring cost estimates

image text in transcribed Note: Implementation of CR 00135 will require procurement of a new tool, which will cost $100,000.

Find the following:

  1. Calculate the nonrecurring costs (cost of implementation) for this change. What is the total?
Resulting Dataset

Total Cost

Type Number Rev Create or Revise Hours Required Rate Per Hour
Total Dataset Cost:
One Time Tooling Cost:
Total Nonrecurring Cost:
  1. Calculate the difference in recurring costs before the change vs. recurring costs after the change for the Wind Turbine (Item 9012).
Recurring Costs (Current)

Total Cost

Hierarchy Purchased Material Direct Labor Overhead Costs
9012 $0 $6,000 $10,000
1234 $0 $4,000 $8,000
4321 (3 per) $0 $2,000 $3,000
8901 $1,000 $0 $0
Recurring Costs (After CR 00135)

Total Cost

Hierarchy Purchased Material Direct Labor Overhead Costs
9012 $0 $6,000 $10,000
1269 $0 $2,000 $6,000
4343 (3 per) $0 $1,000 $2,000
8989 $500 $0 $0
9988 $0 $750 $1,000
8989 $500 $0 $0
7890 (Power Plant Assembly) $0 $100,000 $200,000
.....
  1. Calculate the total number of Wind Turbines that must be produced after the effectivity of the change to fully recover the total costs of implementing the change.
\begin{tabular}{c|c|c|c|} DatasetType & HourstoCreate & HourstoRevise & RateperHour \\ \hline FS & 40.0 & 8.0 & $400 \\ \hline SS & 60.0 & 8.0 & $400 \\ \hline PV & 8.0 & 4.0 & $200 \\ \hline 3D & 60.0 & 8.0 & $200 \\ \hline PP & 8.0 & 4.0 & $200 \\ \hline AD & 12.0 & 6.0 & $200 \\ \hline BM & 8.0 & 4.0 & $200 \\ \hline DD & 12.0 & 6.0 & $200 \\ \hline MS & 12.0 & 3.0 & $200 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting Volume 2

Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield, Irene M. Wiecek, Bruce J. McConomy

13th Canadian Edition

1119740444, 9781119740445

More Books

Students also viewed these Accounting questions

Question

What it the artion of the prits pretut

Answered: 1 week ago

Question

kAk \ infty = kAT k 1 for any matrix A

Answered: 1 week ago