The estimated times and immediate predecessors for the activities in a project at John Black's company are given in the following table. Assume that the

The estimated times and immediate predecessors for the activities in a project at John Black's company are given in the following table. Assume that the activity times are independent. All times are in weeks.

Activity Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b)
A -- 2 4 6
B -- 2 3 10
C A 3 5 7
D B 5 8 17
E C 3 4 11

  1. What is the critical path? You may use any method to determine this.

  1. What is the expected completion time of the project?

  1. What is the probability of completing the project in 17 weeks or more?

  1. What is the probability of completing the project in 14 weeks or less?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Logic For Computer Science Foundations Of Automatic Theorem Proving

Authors: Jean H Gallier

1st Edition

0486805085, 9780486805085

More Books

Students also viewed these Mathematics questions