Question
1 Approved Answer
The estimated times (in weeks), immediate predecessors for the activities, normal cost, crash cost and crash time in a project are given in the following
The estimated times (in weeks), immediate predecessors for the activities, normal cost, crash cost and crash time in a project are given in the following table. Assume that the activity times are independent.
Activity
Immediate predecessors
a
m
b
t
ES
EF
LS
LF
SLACK
A
-
9
10
11
B
A
4
10
16
C
A
8
9
10
D
B
5
8
11
E
B, C
10
12
14
F
D
8
10
12
G
D, E
6
7
8
What is the probability that the project will be completed in 42 weeks or less?
a.67%
b.92%
c.74%
d.68%
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started