The expected activity time in PERT analysis is calculated as: Group of answer choices a. the weighted average of a , m , and b

The expected activity time in PERT analysis is calculated as:

Group of answer choices

a. the weighted average of a, m, and b, with m weighted 4 times as heavily as a and b

b. the sum of the a, m and b, divided by 6

c. the simple average of the a, m and b

d. the sum of the a, m and b

 

Step by Step Solution

3.30 Rating (144 Votes )

There are 3 Steps involved in it

Step: 1

In PERT Program Evaluation and Review Technique analysis the expected ac... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Creating Value Along the Supply Chain

Authors: Roberta S. Russell, Bernard W. Taylor

7th Edition

9781118139523, 0470525908, 1118139526, 978-0470525906

More Books

Students also viewed these General Management questions

Question

What is a reporting entity?

Answered: 1 week ago

Question

Were any of the authors students?

Answered: 1 week ago