The expected daily usage of an item of material is 175 units. The expected lead-time to procure the item is 8 days. The required safety
The expected daily usage of an item of material is 175 units. The expected lead-time to procure the item is 8 days. The required safety stock is 1,000 units. The reorder point is:
a. 2400
b. 1000
c. 100