Question
The factory is in operation 7 hours per shift 2 shifts per day. Daily 400 motors are shipped. Your production cells assembled the frame, 3
The factory is in operation 7 hours per shift 2 shifts per day. Daily 400 motors are shipped. Your production cells assembled the frame, 3 shafts, and 6 bearings. It takes 21 minutes to assemble a frame, 10 minutes to assemble a shaft, and 3.5 minutes to assemble a bearing. What is the pitch?
Step by Step Solution
3.51 Rating (154 Votes )
There are 3 Steps involved in it
Step: 1
total time at pro...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Probability And Statistics For Engineers And Scientists
Authors: Anthony Hayter
3rd Edition
495107573, 978-0495107576
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App