The fast-tracking schedule compression technique usually: a. vastly increases cost b. increases concurrency of activities c. results in unacceptable quality d. enables faster tracking of
The fast-tracking schedule compression technique usually:
a. vastly increases cost
b. increases concurrency of activities
c. results in unacceptable quality
d. enables faster tracking of project progress