The first three tasks of the Surveyor Spacecraft Test & Operations Plan are listed below. Estimate the
Fantastic news! We've Found the answer you've been seeking!
Question:
The first three tasks of the Surveyor Spacecraft Test & Operations Plan are listed below. Estimate the standard deviation of time duration [days] needed to complete all three tasks assuming the tasks occur in sequential order.
Task Duration [days] = (Optimistic, Most Likely, Pessimistic)
Task 1: System Group Test = (28, 32, 40) Task 2: Initial Systems Checkout = (36, 41, 54) Task 3: Mission Sequence Test = (14, 22, 26)