Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The Flapjack Corporation had 7,744 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units,
The Flapjack Corporation had 7,744 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 968 units were actually produced. Labor standards were 7.1 hours per completed unit at a standard rate of $13.00 per hour.
Round your answer to the nearest cent.
The labor time variance is
$7,744.00 unfavorable
$7,744.00 favorable
$11,325.60 unfavorable
$11,325.60 favorable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started