The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A A A 5 B 8
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A A A 5 B 8 C 4 D C 6 E BD 2 F D G EF 6 a. What is the critical path? OA-B-E-G A-C-D-E-G O A-C-D-F-G OA-B-D-F-G b. How many weeks will it take to complete the project? Number of weeks 14 c. How much slack does activity B have?