Question

1 Approved Answer

The following activities are part of a project to be scheduled using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR,TIME ( WEEKS ) ]

The following activities are part of a project to be scheduled using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME (WEEKS)],[A,-,5],[B,A,8],[C,A,4],[D,C,6],[E,Bi D,2],[F,D,3],[G,E, F,6]]
a. What is the critical path?
b. How many weeks will it take to complete the project?
c. How much slack does activity B have?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management An Integrated Approach

Authors: R. Dan Reid, Nada R. Sanders

5th edition

111915880X, 1119158806, 9781118323632, 1118122674, 978-1118122679

More Books

Students also viewed these General Management questions