The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 5 B A 2 C A

The following activities are part of a project to be scheduled using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 5
B A 2
C A 8
D C 3
E B%media:cm.png% D 5
F D 2
G E%media:cm.png% F 8

What is the critical path

A-B-E-G

A-C-D-F-G

A-B-D-F-G

A-C-D-E-G

How many weeks will it take to complete the project

How much slack does activity B have

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Lean Knowledge Management

Authors: Roger Forsgren

1st Edition

1637421338, 978-1637421338

More Books

Students also viewed these General Management questions

Question

Design a server consolidation strategy.

Answered: 1 week ago

Question

Describe the major barriers to the use of positive reinforcement.

Answered: 1 week ago