Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 5 B A 2 C A
The following activities are part of a project to be scheduled using CPM:
ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
---|---|---|
A | 5 | |
B | A | 2 |
C | A | 8 |
D | C | 3 |
E | B%media:cm.png% D | 5 |
F | D | 2 |
G | E%media:cm.png% F | 8 |
What is the critical path
A-B-E-G
A-C-D-F-G
A-B-D-F-G
A-C-D-E-G
How many weeks will it take to complete the project
How much slack does activity B have
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started