1 Approved Answer
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 6 B A 7 C A
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 6 B A 7 C A 2 D C 4 E B, D 5 F D 3 G E, F 7 What is the critical path? multiple choice A-C-D-E-G A-B-E-G A-B-D-F-G A-C-D-F-G How many weeks will it take to complete the project? How much slack does activity B have