The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 6 B A 3
The following activities are part of a project to be scheduled using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D C
E B D
F D
G E F
b What is the critical path?
multiple choice
ABEG
ACDFG
ACDEG Correct
c How many weeks will it take to complete the project?
d How much slack does activity B have?