The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 9 C A

The following activities are part of a project to be scheduled using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 9
C A 5
D C 2
E B%media:cm.png% D 7
F D 6
G E%media:cm.png% F 4

a. What is the critical path?

multiple choice

  • A-C-D-E-G

  • A-B-E-G

  • A-C-D-F-G

  • A-B-D-F-G

b. How many weeks will it take to complete the project?

Number of weeks

c. How much slack does activity B have?

Slack of activity B weeks

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting Creating Value In A Dynamic Business Environment

Authors: Ronald Hilton, David Platt

13th Edition

1264100698, 9781264100699

More Books

Students also viewed these Accounting questions

Question

Write a Python program to check an input number is prime or not.

Answered: 1 week ago