The following are duration estimates for a project: CRITICAL PATH TASKS TASK O M P E V A 1 3 5 3 0 . 4

The following are duration estimates for a project:
CRITICAL PATH TASKS
TASK O M P E V
A 13530.44
B 246
E 1262.50.69
F 137
H 12320.11
TOTAL
OTHER PROJECT TASKS
TASK O M P E V
C 0.5131.250.17
D 12320.11
G 0.5161.750.84
TOTAL
What is the duration of the project? Give your answers to 3 decimal places
Question 8Answer
i.
19.833
ii.
14.250
iii.
14.833
iv.
29.20
v.
20.067

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Operations and Supply Chain Management

Authors: Cecil B. Bozarth, Robert B. Handfield

3rd edition

132747324, 978-0132747325

More Books

Students also viewed these General Management questions