The following are NPV totals for a project's scenario analysis: Worst = -17975.05 (Probabiity 20%), Base = 19,932.82 (Probability 60%), and Best = 57,840.68 (Probability
The following are NPV totals for a project's scenario analysis: Worst = -17975.05 (Probabiity 20%), Base = 19,932.82 (Probability 60%), and Best = 57,840.68 (Probability 20%). Using these numbers, solve for the project's standard deviation of the NPVs. Please show work