The following budgeted information is available: X-Rays Ultrasound CT Scan MRI Total Technician Labour $61,440 $105,600 $96,000 $105,000 $368,040 Depreciation $32,240 $268,000 $439,000 $897,500 $1,636,740
The following budgeted information is available:
X-Rays Ultrasound CT Scan MRI Total
Technician Labour $61,440 $105,600 $96,000 $105,000 $368,040
Depreciation $32,240 $268,000 $439,000 $897,500 $1,636,740
Materials $22,080 $16,500 $24,000 $31,250 $93,830
Administration $20,610
Maintenance $247,320
Sanitation $196,180
Utilities $134,350
Totals $115,760 $390,100 $559,000 $1,033,750 $2,697,070
Number of Procedures 3,840 4,400 3,000 2,500 13,740
Minutes to clean after each proceure 5 5 15 35
Minutes for each procedure 5 15 20 45
Sanitation Minutes 19,200 22,000 45,000 87,500 173,700
Procedure minutes 19,200 66,000 60,000 112,500 257,700
YRC operates at capacity. The proposed allocation bases for overhead are as follows:
Allocation Base Driver
Administration Number of procedures
Maintenance (including parts) Capital cost of equipment (depreciation)
Sanitation Total cleaning minutes
Utilities Total procedure minutes
REQUIRED:
1. Calculate the budgeted cost per service for X-rays, ultrasounds, CT scans, and MRIs using the direct technician labour as the cost allocation base.
2. Calculate the budgeted cost per service for X-rays, ultrasounds, CT scans, and MRIs using activity-based costing (ABC)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started