Question: The following cash flows result from a potential construction contract for Enigma Engineering: ( 1 ) Receipts of $ 5 0 0 , 0 0

The following cash flows result from a potential construction contract for Enigma Engineering:
(1) Receipts of $500,000 at the start of the contract and $1,200,000 at the end of the third year.
(ii) Expenditures of $400,000 at the end of the first year and $600,000 at the end of the second year.
Calculate the approximate ERR of the project. Should Enigma Engineering pursue this project if its MARR is 12%(6 marks)