The following cost information is for Leslie Company. Actual results: Total cost of purchasing material.................................................... $15,000 Number of labor hours worked...................................................... 450 hours Number of
The following cost information is for Leslie Company.
Actual results:
Total cost of purchasing material.................................................... $15,000
Number of labor hours worked...................................................... 450 hours
Number of material pounds used in production.................. 2,000 pounds
Number of units produced............................................................... 200 units
Number of material pounds purchased................................. 1,500 pounds
Total labor cost.................................................................................... $12,500
Leslie Company has established the following standards:
Price per pound of materials............................................... $8.00 per pound
Standard labor rate............................................................... $30.00 per hour
During the year, Leslie Company had an UNFAVORABLE MATERIALS QUANTITY VARIANCE for a total of $3,200. Given these data, what is the standard number of pounds of material needed to produce one unit?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started