The following costs have been estimated for the activities in a project: Activity Immediate Predecessors Time Total Cost($) A - 9 10800 B - 5
The following costs have been estimated for the activities in a project:
Activity | Immediate Predecessors | Time | Total Cost($) |
A | - | 9 | 10800 |
B | - | 5 | 8500 |
C | A | 4 | 6400 |
D | B | 6 | 13620 |
E | C,D | 11 | 9240 |
F | C,D | 5 | 14000 |
G | F | 8 | 7600 |
A.Develop a cost budgeted scheduled based on the earliest start time. Keep once decimal place
B. Develop a cost budgeted schedule based on the latest start time. Keep one decimal place
Please show all work and do not hand write. Thanks!
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started