The following costs have been estimated for the activities in a project: ACTIVITY IMMEDIATE PREDECESSORS TIME TOTAL COST ($) A - 10 13400 B -
The following costs have been estimated for the activities in a project:
ACTIVITY | IMMEDIATE PREDECESSORS | TIME | TOTAL COST ($) |
A | - | 10 | 13400 |
B | - | 5 | 12000 |
C | A | 4 | 5800 |
D | B | 7 | 10500 |
E | C,D | 8 | 9600 |
F | C.D | 4 | 11400 |
G | F | 3 | 3660 |
a) Develop a cost budgeted schedule based on the earliest start time. Please keep one decimal place
b) Develop a cost budgeted schedule based on the latest start time. Please keep one decimal place
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started