Question

1 Approved Answer

The following CPM network has estimates of the normal time in weeks listed for the activities: A network diagram flowchart. The paths of the flowchart

The following CPM network has estimates of the normal time in weeks listed for the activities:
A network diagram flowchart. The paths of the flowchart are as follows. A (5), B (10), D (6), and G (4). A (5), C (8), E (7), and G (4). A (5), C (8), F (4), and G (4).
a-1. Determine the critical path.
multiple choice 1
A-B-D-G
A-C-E-G
A-B-E-G
A-C-F-G
a-2. Determine the early completion time in weeks for the project.
For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened.
ACTIVITY NORMAL TIME NORMAL COST CRASH TIME CRASH COST
A 5 $ 7,0003 $ 13,000
B 1012,000718,000
C 85,00077,000
D 64,00055,000
E 73,00066,000
F 46,00037,000
G 47,00039,000
b-1. Which activities in order of reduction would be shortened?
multiple choice 2
D-G-A
G-D-A
A-G-D
D-B-C

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

High Output Management

Authors: Andrew S. Grove

2nd Edition

9780679762881

More Books

Students also viewed these General Management questions

Question

understand possible effects of lifestyle risk factors;

Answered: 1 week ago