The following CPM network has estimates of the normal time in weeks listed for the activities: a - 1 . Determine the critical path. A
The following CPM network has estimates of the normal time in weeks listed for the activities:
a Determine the critical path.
ACFG
ABEG
ACEG
ABDG
a Determine the early completion time in weeks for the project.
Early completion time
weeks