The following data are given for Harry Company: Budgeted production 1,076 units Actual production 929 units Materials: Standard price per ounce $1.859 Standard ounces per

The following data are given for Harry Company:

Budgeted production 1,076 units
Actual production 929 units
Materials:
Standard price per ounce $1.859
Standard ounces per completed unit 10
Actual ounces purchased and used in production 9,569
Actual price paid for materials $19,616
Labor:
Standard hourly labor rate $14.39 per hour
Standard hours allowed per completed unit 4.6
Actual labor hours worked 4,784
Actual total labor costs $77,740
Overhead:
Actual and budgeted fixed overhead $1,153,000
Standard variable overhead rate $26.00 per standard labor hour
Actual variable overhead costs $133,952
Overhead is applied on standard labor hours. (Round interim calculations to the nearest cent.)

The direct labor rate variance is

a.$16,245.77 favorable

b.$16,245.77 unfavorable

c.$8,898.24 favorable

d.$8,898.24 unfavorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Accounting

Authors: Frederick D. S. Choi, Gary K. Meek

7th Edition

0136111475, 9780136111474

More Books

Students also viewed these Accounting questions

Question

What is manufacturing cycle efficiency? LO5

Answered: 1 week ago

Question

why you want to attend graduate school in general;

Answered: 1 week ago